Employing over 500 people and based in ten countries, this automotive company supplies components for all major diesel market segments, including cars, light vans, heavy commercial vehicles and agricultural, industrial and marine vehicles.

Who we worked with

With a view to expanding its global aftermarket presence, the client approached CDC to design and build 8No modular environmental test cells to guarantee accurate and repeatable product testing.

What we did

Size : 170m2

Duration : 12 weeks

Cost : £350,000

Details :

Principle Contractor √

Design & Build √

Live Site √

Contract Type JCT √

Project Planning √

Project Management √

Construction & Fit-out √

HVAC & Ventilation √

Piped Services √

Electrics √

Test & Commission √

Validation

How we did it

With specific ‘close control’ of the room acoustics as well as temperature and humidity required, we constructed the room modules around a structural steel frame to support all plant and services directly above.