Following rigorous competitive tender and subsequent post tender technical analysis, CDCfm secured this prestigious cleanroom project for aseptic processing through clear demonstration of technical compliance and ability to deliver a complex facility within a live hospital environment.

Who we worked with
Project Type : Aseptic
Size : 62m2
Duration : 12weeks
Cost : £240,000

What we did
Principle Contractor √
Design & Build √
Live Site √
Contract Type JCT √
Project Planning √
Project Management √
Construction & Fit-out √
HVAC & Ventilation √
Piped Services √
Electrics √
Test & Commission √
Validation (MHRA) √

How we did it
Operating as specialist designer and main contractor CDCfm’s responsibilities included direct liaison with the client user team to demonstrate full URS compliance.
With detailed design and coordinated project programming implemented from the outset to ensure the project delivery absolutely minimised the impact to patients, staff and public within this busy city hospital.
The high quality of architectural finishes blended with the necessary engineering expertise ensured the successful delivery of the suite which subsequently allowed MHRA validation to be achieved at first inspection.